Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
Search representations
Results for Environment Agency search
New searchComment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE15/H - Proctor Street playing fields, Off Tong Street, Holme Wood
Representation ID: 28965
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE16/H - Holme Lane, Holme Wood
Representation ID: 28966
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE17/HC - Kesteven Road/Heysham Drive, Holme Wood
Representation ID: 28967
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE18/H - Ned Lane, Holme Wood
Representation ID: 28968
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE19/H - Westgate Hill Street Tong
Representation ID: 28969
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE20/H - Dean Beck Avenue
Representation ID: 28970
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE21/H - New Lane, Laisterdyke
Representation ID: 28971
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE22/H - Furnace Road, Oakenshaw
Representation ID: 28972
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE23/HC - Tennis Avenue
Representation ID: 28973
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
SE24/HC - Upper Castle Street
Representation ID: 28974
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.