Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY20/HC - Redwood Close

Representation ID: 28654

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.

For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.

Comment

Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY21/HC - Parkwood Rise

Representation ID: 28656

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.

For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.

Comment

Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY22/H - Parkwood Rise

Representation ID: 28658

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.

For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.

Object

Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY23/H - Walk Mills, The Walk

Representation ID: 28659

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site is identified to be either wholly, or most of, in the current/draft 3b OR 3a(i) - Site is in FZ2 and 3. Half the site is impacted by the current 3ai extent and psrt of the site is impacted by the 2019 draft 3b extent. This will be a topic for the SFRA, possibility to become 3b land

This is a key aspect of conversation as part of the pending SFRA update as such no allocations should be made in these areas unless considered water compatible or essential infrastructure. Where this is the case the development must demonstrate no increase in risk to others, no loss of Functional Floodplain and suitable mitigation measures for use and the lifetime of the development.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.

For development near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles. Some SuDs principles such as storage ponds should not be solely relied upon within areas at risk of fluvial flooding as they may not be operational during a flood.

Object

Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY24/H - Marriner Road

Representation ID: 28660

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site is identified to be either wholly, or most of, in the current/draft 3b OR 3a(i) - Site is in FZ3 and fully in 3ai but not within in current 2019 3b draft extent. This will be a topic for the SFRA, possibility to become 3b land

This is a key aspect of conversation as part of the pending SFRA update as such no allocations should be made in these areas unless considered water compatible or essential infrastructure. Where this is the case the development must demonstrate no increase in risk to others, no loss of Functional Floodplain and suitable mitigation measures for use and the lifetime of the development.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.

For development near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles. Some SuDs principles such as storage ponds should not be solely relied upon within areas at risk of fluvial flooding as they may not be operational during a flood.

Comment

Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY25/H - Hainworth Road

Representation ID: 28665

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.

For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.

Comment

Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY26/H - Hainworth Road

Representation ID: 28666

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.

For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.

Comment

Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY27/H - Hainworth Lane/ Halifax Road

Representation ID: 28667

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.

For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.

Comment

Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY28/H - Staveley Way

Representation ID: 28669

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site in Flood Zone 1 ONLY - Close proximity to FZ2 and 3 and the current 3ai allocation. As such situation can change post SFRA update.

Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.

For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.

Comment

Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021

KY29/H - Woodhouse Road

Representation ID: 28670

Received: 24/03/2021

Respondent: Environment Agency

Representation Summary:

Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).

If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.

For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.

For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.

It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.

Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.