BI2/HC - Sty Lane
Representation ID: 28704
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY - Close to canal.
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
BI3/H - Greenhill Barn, Lady Lane
Representation ID: 28705
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
BI4/H - Heights Lane (west side), Eldwick
Representation ID: 28706
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
BI5/H - Crossley Wood Road, Gilstead
Representation ID: 28707
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY - Close to canal.
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
BI6/H - Marley Court, Crossflatts
Representation ID: 28708
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY - Close to canal
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
BI7/H - Whitley Street
Representation ID: 28709
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
BI8/H - Land west of Heights Lane, Eldwick
Representation ID: 28710
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
HR1/H - Chelston House
Representation ID: 28711
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
HR2/H - South Walk
Representation ID: 28712
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.
Comment
Draft Bradford District Local Plan - Preferred Options (Regulation 18) February 2021
HR3/H - Long Lane
Representation ID: 28713
Received: 24/03/2021
Respondent: Environment Agency
Site in Flood Zone 1 ONLY
Mitigation should be set above the 1 in 100 plus cc level for the site as suitable for the proposed vulnerability classification (EA standing advice should cover this).
If the site is considered Greenfield then surface water discharge rates post development should be restricted to the pre development Greenfield discharge rate. If the site is considered Brownfield then there should be a 30% reduction in surface water discharges, or restricted to Greenfield rates, there should be no increase in brownfield surface water discharge rates post development. So as to support prevention of cumulative increases to flood risk and should be in line with SuDs design principles.
For developments near ordinary watercourses we would recommend an 8 metre easement strip along the length of the riverbank, or a 45degree angle from the bed in the case of culverts, to be kept clear of permanent structures such as buildings. This is to maintain access to the riverbank for any improvements or maintenance. A Flood Defence Consent may be required for the LLFA for works in/affecting an ordinary watercourse.
For main rivers, we generally require an 8 metre easement strip along the length of the riverbank to be kept clear of permanent structures such as buildings, or a 45degree angle from the bed in the case of culverts. This is to maintain access to the riverbank for any improvements or maintenance. Environmental Flood Risk Activity Permits may be required for development near rivers.
It is possible the sites within close proximity to Flood Zones 3b, 3 and 2 may be subject to future risk identified within the SFRA (to follow) which may affect its allocation or how development should be sequentially laid out on the site.
Consideration must be made to making space for water and providing betterment in terms of flood risk management where ever possible.